Wednesday, July 31, 2013

Lessons learnt and apartment update!

The first and most important rule is that Things do go wrong and they WILL. No matter how well the project was planned. Execution is a totally different ball game.

A few things I have learnt during the new apartment interiors process -

* Everything that you want to change, fix, break, restructure is mostly possible. If your contractor/designer/carpenter says otherwise, it could be because he doesn't want the additional headache, too much risk involved, lack of expertise, it costs too much money (which should be a headache for you not your designer or contractor). Only a very small number of exceptions exist to this almost-fact.

* Double check everything before it gets executed. The design does go through changes while it passes from the designer's table to the supervisor to the carpenter who works on it! So make sure you tell the carpenter or handyman to show a rough draft of what he has understood or show the assembled piece before fixing it finally. Trust me this will go a long way to help avoid major blunders.

* We Indians as a generic trait have a tendency to nod our heads and say yes to everything. Then later on we actually ponder over whether the task can be done or not. And we also have a tendency to hide things from the client till the end. The husband says, If something goes wrong, then a project coordinator should either fix it OR if it cannot be fixed and will cause a delay then the client should be informed. Most of the contractors/carpenter teams don't do either. They let the project linger on and complete it on its own pace. Keep an eye out for this. And if possible make your own schedule with dates of starting and completion and track the work as per that, raising a red flag when needed.

* Electrical points - If you have the option of changing electrical points and choosing where you want them then do it. Do it before you start the actual wood work - cupboards, bookshelves etc. Think of where would you want reading lights to be fixed, lamps to be kept with respect to beds and bedside tables. I personally like to have switches and a plug point next to the bed on both sides. The getting out-of-bed to switch the light off is one thing I don't like. Charging mobile phones or laptops is also convenient when you have a plug point next to your bed.

* Don't forget the geyser in the kitchen for those oh-so-cold winter days. Your house help is going to be thankful!

* Thinking of buying a Home theater system at some point of time in the future? Get the points for speakers and the system in place. The points can be done and left and used later.

* Have a terrace or balcony - make sure you have enough light and plug points for all those barbecue and late night parties.

Updates from the new apartment -
We are at a stage where the electricals in the new apartment have mostly been completed. The carpentry for the wood work - wardrobes, bookshelf, study desk, bar unit and a few other storage shelves in the kid's room are mostly done. Now the surface finishing work shall start - duco, veneer polishing, laminate fixing etc. Another 15 to 20 days to go.

Sneak peek into the home! Tada till the next time :)


One of my favourites (already) in the house - the bookshelf 

One of the corners in the living room - waiting to see it come together with the lights



3 comments:

  1. Loved the pic of that wall on FB, only now managed to hop across and read the tips. I let out a small sigh of relief, most of that stuff is taken care of for my current apartment at least! For the house that I live in, I did learn a lot of this along the way too, wish you'd done your home/interiors a few years back and I could have read this earlier :P

    All the best and looking forward to pics of the further progress :).

    ReplyDelete
    Replies
    1. Thanks Aparna!! I am waiting to breathe out that sigh of relief :) For now it seems like an endless and huge task. There is still so much to be done. Trying to be patient.

      Delete
  2. Hey Simran,

    I'm thinking of a structural change pretty late in the day and remembered this post. I'm told by the site engineer that breaking a wall now will lead to cracks later. I suspect that is because he doesn't want to do the job. Any idea if what he's saying is true?

    ReplyDelete

What do you think? I would love to know!

LinkWithin

Related Posts Plugin for WordPress, Blogger...